CLIENT
Equibuild
PROJECT
The Grange School
VALUE
£55,000
TIMESCALE
20 Weeks
All works were delivered to a high standard and in full compliance with current electrical regulations, ensuring the new space was fully operational, safe, and ready for immediate use upon project completion.
Phase 1
Carried out over the 2022 summer break, focused on enabling works, including coordination with civil and groundworks teams to prepare infrastructure for future electrical systems
Phase 2
Encompassed the main build, during which Orchard carried out the installation of power and lighting systems, fire alarm integration, CCTV infrastructure, data and comms cabling, and containment systems throughout the new facility.